  1. Create PowerBI Report in Power BI Desktop .
  2. Save  the report to box folder IT-BIA\Projects\PowerBI\Projectname\Dev    (Note:Change project name to name of your project Eg Travel etc)
  3. Publish report to Dev workspace (IT BIA Power BI Dev GRP).
  4. Review the report 
  5. Once PO review is complete ,publish the report to prod workspace. If the project has its own workspace ,publish the report to the project workspace and update the app.

...