Jump to Meeting Notes

Project Status

...

5/31/2023 College Accountabilty Phase 2 - Status Meeting Agenda and Notes

  • Show Jira plan and CA board with items moved to phase 2. Done

  • Update on Slalom contract - Sarah Thomas

  • Deliverables for Slalom - Still in progress

    • Determine maximum 10 metrics for Slalom to work with

    • Determine which data sources these metrics come from, cannot exceed 5 data sources

    • Determine which systems that Slalom consultants will need access to

    • Determine who are the SMEs for these metrics and data sources

  • Set up for Slalom (netid, global protect, vpn, and access to systems) - Need someone to coordinate - Jay volunteered for this.

  • Review first draft of schedule that Sangita has set up. This may not be complete, but it will give her an opportunity to ask questions and get feedback. Still in progress.

  • Sarah to add the following tasks to Jira (groups approval). Reviewed with meeting attendees and assignments made.

    • Slalom information set up (Sangita and Shruti?)

    • Slalom access (TBD?Jay)

    • Slalom workshop scheduling on Teams Sarah Thomas Meeting invitation sent by Slalom.

    • Data Model Analysis and Design (Sangita/Shruti?)

    • Data Model Implementation (TBD)

    • Metrics to include design of report and SQL for data pull (Sangita/Hennadii/Xiaoying?) for 5 Year Trends - this will be for all metrics that we included for Phase 1 - ACTUALLY NO, We reviewed a list of metrics that should be included. See Project Decisions for 5/31.

    • Website design changes (Shruti)

    • Website modifications (Chirag)

  • Proposed Timeline to review - Not ready to review

    • Analysis and design of data model for Phase 2 and Phase 3 (June 1-July 15)

    • Development of Data Model (July 1-31)

    • Analysis, design and development of Point-In-Time data pulls and dashboard design (July 15 - Aug. 15)

    • Website modifications (Aug. 14-21)

    • QA and approval of Dashboards (Aug. 1-31)

    • Go Live for Point-In-Time Dashboards (Sept. 1)

...