This page is dedicated to documenting the processes/links for the SIS/SAP Migration to Power BI
Purpose: Bringing consistency with reports at the university on a newer, modern platform, reducing user maintenance, and enabling full ownership of the reporting solution by ODS and URO.
The current SAP reports which require IT intervention for user access and report management will be unavailable when the contract with SAP expires.
The reports that will be converted first will be the reports that are ran most, with their creation date taken into account.
Number of Reports:
URO: 101
Originally 176
Retire 2
Already transferred 73
ODS: 374
User Acceptance Testing:
Users will need to sign up to test newly converted reports.
If no one signs up for a certain report, the report will not be converted.
UAT sign-up sheet: https://usf.box.com/s/0w778l2jje2mox4m5idf5lo6shrhsche
Migration Timeline Below: